A, B and C can complete a work, working alone in 10, 15 and 20 days respectively. If all of them work together to complete the work, what fraction of the work would have done by B?

 12 

 13 

 413 

 613 

JEE Advance
College PredictorLive

Know your College Admission Chances Based on your Rank/Percentile, Category and Home State.

Get your JEE Main Personalised Report with Top Predicted Colleges in JoSA

Solution
Verified BY
Verified by Zigyan

Ratio of rate of working of A,B and C is

 110:115:120 

= 6 : 4 : 3

Thus, B would do = 46+4+3=413 of the total work.